Friday, July 8, 2011

A Look Ahead: Transbay Demolition and Construction Activities




BOMA San Francisco Members:

This week at Transbay...

TRAFFIC UPDATE: Mission Street is currently closed in both directions between First and Fremont Streets due to an incident involving the Muni overhead wires. Please revise your route home accordingly.

Weekend Work (7/9/11 – 7/10/11):

Fremont Street: Underground sewer work will occur at the intersection of Fremont and Natoma Streets on Saturday, July 9 and Sunday, July 10 from 9:00 AM to 5:00 PM. Lanes will be reduced along Fremont Street to accommodate this work.

Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue in the east and west lots on Saturday, July 9 from 8:00 AM to 5:30 PM.

Weekday Work (7/11/11 – 7/15/11):

Overnight Shift - Work between the hours of 11:00 PM and 07:00 AM. There are no planned activities next week.

Evening Shift - Work between the hours of 7:00 PM and 11:00 PM. There are no planned activities next week.

Day Shift - All contractors will work between the hours of 7:00 AM and 7:00 PM. Activities will include:

Trenching:

Work will continue on both Minna Street between Second and First Streets and on Natoma Street between Fremont and Second Streets - Day Shift.

Shoring & Excavation Preparation:

Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue in the east lot, while trenching and preparation activities will continue in the central and west transit center sites. Shoring wall test panel installation will take place in the west lot - Day Shift.

Demolition:

Natoma Street: Demolition work will continue on selected buildings along Natoma Street in the lot between Howard and Natoma Streets - Day Shift.

Underground utilities/ trenching work:

Second & Natoma Street Intersection: Underground trenching and utilities work - Day Shift.

Beale Street (from Mission to Howard Streets): Underground utilities work, sidewalk and pavement repairs - Day Shift.

Fremont Streets (from Mission to Howard Streets): Underground trenching and utilities work - Day Shift.

Detours, Street and Sidewalk Closures:

The following streets will be temporarily impacted due to project activities. So you can plan ahead please review the affected streets below:

Second Street: Lane restrictions will be in effect on Second Street between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.

Natoma Street: Local access only will be allowed on Natoma Street. There will be a partial street closure and parking prohibition in effect on Natoma Street between Fremont and Second Streets from 7:00 AM to 5:00 PM. There will be an SFPD 10B officer or flagger on site to direct access.

Minna Street: Local access only will be allowed on Minna Street. There will be a partial street closure and parking prohibition in effect on Minna Street between First and Second Streets from 7:00 AM to 5:00 PM. There will be an SFPD 10B officer or flagger on site to direct access.

Beale Street: The east sidewalk of Beale Street between Mission and Howard Streets will remain closed. Pedestrians will be diverted into a temporary sidewalk in the parking lane of Beale Street through Saturday, July 30, 2011. Pedestrians are advised to use the west side of Beale Street until further notice. Lane restrictions will remain on Beale Street between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.

Fremont Street: Lane restrictions will be in effect on Fremont Street between Mission and Howard Streets between the hours of 9:00 AM and 5:00 PM. The east sidewalk of Fremont Street between Mission and Howard Streets will remain closed. Pedestrians must use the west side of Fremont Street until further notice.

What to Expect Next Weekend (7/16/11 - 7/17/11):

Muni OCS pole relocation will take place on Beale Street Saturday, July 16 and Sunday, July 17.

Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue in the east lot on Saturday, July 16 from 8:00 AM to 5:30 PM between Beale and Fremont Streets.

Questions?

Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org

Construction Hotline:

If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).

Website:

Please continue to check this website for the most up to date schedule of activities at: http://transbaycenter.org/construction-updates/updates-notices/current-activity

Public Transit:

The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs: http://511.org/ or visit www.temporaryterminal.org

No comments:

Post a Comment

Apture