Monday, February 7, 2011

A Look Ahead: Transbay Demolition and Construction Activities




BOMA San Francisco Members:

Weekday Work: Weekday work will take place between Monday, February 7, 2011 and Friday, February 11, 2011. All contractors will work between the hours of 7:00 AM and 9:00 PM. Demolition activity to demolish the East Terminal building basement slab will continue into mid-February.

Demolition activity will continue through February at both the Center Terminal building and West Terminal building.

Demolition activity will take place at the old concrete traffic island on First Street between Mission and Howard Streets.

Underground utilities work will continue and include:
  • Continued underground utilities work on the Howard and Fremont Street intersection on Monday night from 8:00 PM-5:00 AM. The work will be performed during these hours due to concerns by Caltrans for Fremont Street off ramp traffic.
  • Continued underground utilities work on First Street from Mission to Howard Streets. 
  • Continued underground utilities work on Howard Street from Beale to Fremont Streets. 
  • Continued underground utilities work on Howard Street from Fremont to First Streets. 
  • Continued underground utilities work on Minna Street from First to Second Streets. 
  • Continued underground utilities work on Natoma Street from First to Second Streets. 
  • Continued underground utilities work on Shaw Alley between Mission and Minna Streets. 
Street and Sidewalk Closure: Lane restrictions will remain on Minna Street and Natoma Street between First and Second Streets. All affected buildings will be granted full access to their parking garages and loading docks.

Shaw Alley will be closed between Mission and Howard Streets between the hours of 7:00 AM and 5:00 PM.

Lane restrictions will remain on Fremont Street between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.

Lane restrictions will remain on First Street between Mission and Howard Streets between the hours of 7:00 AM and 3:00 PM.

Lane restrictions will be in effect on Howard Street between Fremont and First Streets between the hours of 9:00 AM and 3:00 PM.

The sidewalk on the east side of Fremont Street will remain closed. Pedestrians must use the west side of Fremont Street until further notice.

What to Expect Next Weekend (2/12/11 – 2/13/11): Underground utility work will continue on Howard Street between Main and Beale Streets (in front of the Temporary Terminal) between the hours of 8:00 AM and 7:00 PM on Saturday and Sunday.

Underground Utility work will continue along Minna Street between the hours of 8:00 AM and 5:00 PM Saturday, February 12, 2011.

Demolition work will continue on Saturday, February 12, 2011 between the hours of 8:00 AM and 5:00 PM, at the West Terminal Building. The Crusher/Conveyors will be in operation at the Center Terminal.

Thank you to all those who attended this month’s community meeting. Your continued participation and interest in the project is greatly appreciated. We look forward to seeing you at our next community meeting in March!

Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org.

If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).

Please continue to check our website for the most up to date schedule of activities at: www.transbaycenter.org/demolition

No comments:

Post a Comment

Apture